PMI-RMP Practice Questions
648 real PMI-RMP exam questions with expert-verified answers and explanations. Page 1 of 13.
- Question #1Perform Targeted Risk Analysis
Examine the figure given below. What will be the expected monetary value of Risk C?
Expected Monetary Value (EMV)Quantitative Risk AnalysisRisk ImpactRisk Probability - Question #2Stakeholder Engagement
John is the project manager of the NHQ Project for his company. His project has 75 stakeholders, some of which are external to the organization. John needs to make certain that he...
Communication PlanningStakeholder EngagementRisk CommunicationProject Management Plans - Question #3Perform Targeted Risk Analysis
You are the project manager of the KJH Project and are working with your project team to plan the risk responses. Consider that your project has a budget of $500,000 and is expecte...
Expected Monetary Value (EMV)Quantitative Risk AnalysisRisk ExposureRisk Response Planning - Question #4Perform Targeted Risk Analysis
Which one of the following is the only output for the qualitative risk analysis process?
Qualitative Risk AnalysisProcess OutputsRisk Register - Question #5Perform Targeted Risk Analysis
Jeff, a key stakeholder in your project, wants to know how the risk exposure for the risk events is calculated during quantitative risk analysis. He is worried about the risk expos...
Quantitative Risk AnalysisRisk ExposureExpected Monetary ValueProbability and Impact - Question #6Risk Strategy and Planning
You are the project manager of the YHG project for your company. Within the project, you and the project team have identified a risk event that could have a financial impact on the...
Risk Response StrategiesMitigationThreat ResponseProbability Reduction - Question #7Risk Strategy and Planning
You are the project manager of the NKJ Project for your company. The project's success or failure will have a significant impact on your organization's profitability for the coming...
Risk utility functionRisk toleranceStakeholder toleranceRisk attitude - Question #8Perform Targeted Risk Analysis
You are the project manager for your organization. You are working with your key stakeholders in the qualitative risk analysis process. You understand that there is certain bias to...
Qualitative Risk AnalysisStakeholder BiasProbability and Impact ScalesRisk Assessment Techniques - Question #9Risk Monitoring and Reporting
Your organization, as part of its enterprise environmental factors, has established risk governance to be implemented in each project. Part of this governance is the reassessment o...
Risk ReassessmentRisk Monitoring and ControlAdaptive Risk ManagementTailoring Risk Management - Question #10Risk Process Facilitation
Your project spans the entire organization. You would like to assess the risk of the project but are worried that some of the managers involved in the project could affect the outc...
Risk Identification TechniquesDelphi TechniqueAnonymous Risk Identification - Question #11Stakeholder Engagement
Frank is the project manager of the NHL Project for his company and he is starting the risk identification process for the project. Frank needs to ensure that the correct stakehold...
Stakeholder identificationStakeholder engagementRisk identificationProject documents - Question #12Perform Targeted Risk Analysis
You are working with your project stakeholders to identify risks within the JKP Project. You want to use an approach to engage the stakeholders to increase the breadth of the ident...
Risk identificationSWOT analysisInternal risksRisk identification techniques - Question #13Risk Monitoring and Reporting
Ted is the project manager of the HRR project for his company. Management has asked that Ted periodically reviews the contingency reserve as risk events happen, pass, or are still...
Contingency ReserveRisk MonitoringReserve AnalysisRisk Exposure - Question #14Perform Targeted Risk Analysis
Which of the following documents is described in the statement below? "It is developed along with all processes of the risk management. It contains the results of the qualitative r...
Risk RegisterRisk Management DocumentationQualitative Risk AnalysisQuantitative Risk Analysis - Question #15Perform Targeted Risk Analysis
Fred is the project manager of the CPS project. He is working with his project team to prioritize the identified risks within the CPS project. He and the team are prioritizing risk...
Qualitative risk analysisRisk prioritizationProbability and impact assessmentRisk analysis techniques - Question #16Risk Monitoring and Reporting
Which of the following statements describe the purpose of an Issue Log? Each correct answer represents a complete solution. Choose all that apply.
Issue LogIssue ManagementTrackingProject Documentation - Question #17Risk Process Facilitation
You are the program manager for your organization. Management is considering a new program but they are worried about the program risks that may affect the program success. You kno...
Risk response strategiesThreat responsesTransferenceThird-party risk management - Question #18Risk Strategy and Planning
There are seven risk responses for any project. Which one of the following is a valid risk response for a negative risk event?
Risk response strategiesNegative risksThreatsRisk planning - Question #19Risk Strategy and Planning
Bill is the project manager of the JKH Project. He and the project team have identified a risk event in the project with a high probability of occurrence and the risk event has a h...
Risk Response StrategiesThreat ResponsesRisk Avoidance - Question #20Risk Monitoring and Reporting
Your project team has identified a project risk that must be responded to. The risk has been recorded in the risk register and the project team has been discussing potential risk r...
Risk responseCorrective actionRisk controlProject monitoring and controlling - Question #21Risk Monitoring and Reporting
Beth is the project manager of the BFG Project for her company. In this project Beth has decided to create a contingency response based on the performance of the project schedule....
Schedule VarianceEarned Value ManagementProject Performance Measurement - Question #22Perform Targeted Risk Analysis
During which of the following processes, probability and impact matrix is prepared?
Qualitative Risk AnalysisProbability and Impact MatrixRisk Management ProcessRisk Analysis Tools - Question #23Risk Strategy and Planning
Holly is the project manager of the GHH Project. During risk identification and the subsequent risk analysis process she has identified a risk with a high probability and high impa...
Risk response strategiesRisk avoidanceThreat responseProject management plan changes - Question #24Risk Process Facilitation
Tom works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in iden...
Identify RisksInputs to Identify RisksActivity Cost EstimatesRisk Identification Techniques - Question #25Risk Strategy and Planning
Frank is the project manager of the NHH Project. He is working with the project team to create a plan to document the procedures to manage risks throughout the project. This docume...
Risk management planRisk planningRisk proceduresContingency planning - Question #26Risk Monitoring and Reporting
Holly is the project manager of the NSS Project for her company. She is discussing some of the project risks and the issues that have happened in the project. Holly has faxed the s...
Communication ModelProject CommunicationStatus Reporting - Question #27Risk Monitoring and Reporting
Pete works as a project manager for BlueWell Inc. The Management has told him that he must implement an agreed-upon contingency response if the cost performance index in his projec...
Earned Value Management (EVM)Cost Performance Index (CPI)Contingency ResponsePerformance Measurement - Question #28Risk Monitoring and Reporting
You work as a project manager for BlueWell Inc. You are working with Nancy, the COO of your company, on several risks within the project. Nancy understands that through qualitative...
Risk documentationWatchlistLow probability low impact risksRisk monitoring - Question #29Risk Monitoring and Reporting
There are four inputs to the Monitoring and Controlling Project Risks process. Which one of the following will NOT help you, the project manager, to prepare for risk monitoring and...
Risk MonitoringPMBOK ProcessesProcess InputsRisk Control - Question #30Risk Strategy and Planning
A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk respons...
Risk response strategiesRisk transferenceOutsourcingRisk management - Question #31Risk Strategy and Planning
You work as a project manager for BlueWell Inc. You are working with your team members on the risk responses in the project. Which risk response will likely cause a project to use...
Risk responsesOpportunity managementRisk sharingProcurement processes - Question #32Perform Targeted Risk Analysis
During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?
Qualitative Risk AnalysisRisk PriorityRisk UrgencyRisk Indicators - Question #33Perform Targeted Risk Analysis
Which of the following processes is described in the statement below? "This is the process of numerically analyzing the effect of identified risks on overall project objectives."
Quantitative Risk AnalysisRisk AnalysisProject Risk ManagementNumerical Analysis - Question #34Risk Monitoring and Reporting
Ruth is the project manager of ISFH project for her company. This project is forty percent complete and it appears that some risk events are going to happen in the project that wil...
Change RequestsRisk ResponseCorrective ActionsContingency Plans - Question #35Perform Targeted Risk Analysis
Henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in th...
Configuration managementChange controlProduct scopeIntegrated change control - Question #36Stakeholder Engagement
You are the project manager for BlueWell Inc. Your current project is a high priority and high profile project within your organization. You want to identify the project stakeholde...
Stakeholder AnalysisPower-Interest GridStakeholder Identification - Question #37Risk Monitoring and Reporting
You work as the project manager for BlueWell Inc. You are monitoring the project performance. You want to make a decision to change the project plan to eliminate a risk in order to...
Risk avoidanceThreat responseRisk response strategiesProject monitoring - Question #38Risk Process Facilitation
Lisa is the project manager of the FKN project for her organization. She is working with Sam, the CIO, to discuss a discount the vendor has offered the project based on the amount...
Positive Risk ResponseOpportunity ManagementRisk Acceptance (Opportunity)Risk Register - Question #39Perform Targeted Risk Analysis
You are preparing to complete the quantitative risk analysis process with your project team and several subject matter experts. You gather the necessary inputs including the projec...
Quantitative Risk AnalysisCost Management PlanRisk Analysis Inputs - Question #40Risk Strategy and Planning
You and your project team are identifying the risks that may exist within your project. Some of the risks are small risks that won't affect your project much if they happen. What s...
Risk identificationRisk response strategiesRisk watchlistLow priority risks - Question #41Perform Targeted Risk Analysis
You are the project manager of a new project in your organization. You and the project team have identified the project risks, completed risk analysis, and are planning the most ap...
Risk response planningQuantitative risk analysisDecision tree analysisExpected Monetary Value (EMV) - Question #42Risk Strategy and Planning
You are the project manager of the NNQ Project for your company and are working with your project team to define contingency plans for the risks within your project. Mary, one of y...
Contingency PlanningRisk Response StrategiesRisk Management ProcessRisk Definition - Question #43Stakeholder Engagement
Who is responsible for the stakeholder expectations management in a high-profile, high-risk project?
Stakeholder Expectations ManagementProject Manager ResponsibilitiesStakeholder Engagement - Question #44Risk Strategy and Planning
You are completing the qualitative risk analysis process with your project team and are relying on the risk management plan to help you determine the budget, schedule for risk mana...
Risk categoriesPlan Risk Management processRisk Management PlanProject planning - Question #45Risk Monitoring and Reporting
You are the project manager of the HJH project for your company. In your project, you have created the probability-impact risk matrix as shown in the following figure: If Risk D ha...
Contingency ReserveRisk Response ImplementationRisk BudgetingQuantitative Risk Analysis - Question #46Perform Targeted Risk Analysis
The only output of the perform qualitative risk analysis are risk register updates. When the project manager updates the risk register he will need to include several pieces of inf...
Qualitative Risk AnalysisRisk Register UpdatesRisk Tools and TechniquesRisk Prioritization - Question #47Perform Targeted Risk Analysis
Nancy is the project manager of the NHH project. She and the project team have identified a significant risk in the project during the qualitative risk analysis process. Bob is fam...
Risk Management ProcessQualitative Risk AnalysisQuantitative Risk AnalysisRisk Response Planning - Question #48Perform Targeted Risk Analysis
Which of the following diagrams displays sensitivity analysis data?
Sensitivity analysisTornado diagramRisk analysisQuantitative risk analysis - Question #49Risk Strategy and Planning
Rachel is the project manager of the KJH Project for her company. She needs a method to create a quick and simple approach to risk identification to communicate the project risk wi...
Risk IdentificationChecklist AnalysisRisk Management TechniquesProject Risk Management - Question #50Risk Strategy and Planning
Shawn is the project manager of the WHT Project for his company. In this project Shawn's team reports that they have found a way to complete the project work for less cost than wha...
Risk response strategiesOpportunity managementExploiting opportunitiesPositive risk responses