PMIPMI
PMI-RMP · Question #44
PMI-RMP Question #44: Real Exam Question with Answer & Explanation
The correct answer is B: Plan risk management process. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
You are completing the qualitative risk analysis process with your project team and are relying on the risk management plan to help you determine the budget, schedule for risk management, and risk categories. You discover that the risk categories have not been created. When should the risk categories have been created?
Options
- ACreate work breakdown structure process
- BPlan risk management process
- CRisk identification process
- DDefine scope process
Topics
#Risk categories#Plan Risk Management process#Risk Management Plan#Project planning
Community Discussion
No community discussion yet for this question.