At the time the risk register is first prepared, it should contain all the following entries EXCEPT______________

The correct answer is C. List of risks requiring near-term responses. When the risk register is first created during the Identify Risks process, it contains the structure for describing risks (B), root causes of risk (A), and a preliminary list of potential responses (D). A 'list of risks requiring near-term responses' (C) requires…

Risk Strategy and Planning

Question

At the time the risk register is first prepared, it should contain all the following entries EXCEPT______________

Options

  • ARoot causes of risk
  • BStructure for describing risks
  • CList of risks requiring near-term responses
  • DList of potential responses

How the community answered

(60 responses)
  • A
    2% (1)
  • B
    5% (3)
  • C
    92% (55)
  • D
    2% (1)

Explanation

When the risk register is first created during the Identify Risks process, it contains the structure for describing risks (B), root causes of risk (A), and a preliminary list of potential responses (D). A 'list of risks requiring near-term responses' (C) requires prioritization, which only happens after qualitative and/or quantitative risk analysis has been performed. That level of prioritization cannot exist at the initial identification stage, making C the correct exception.

Topics

#Risk Register Content#Initial Risk Management#Risk Identification#Risk Management Planning