PMI-RMP · Question #281
At the time the risk register is first prepared, it should contain all the following entries EXCEPT______________
The correct answer is C. List of risks requiring near-term responses. When the risk register is first created during the Identify Risks process, it contains the structure for describing risks (B), root causes of risk (A), and a preliminary list of potential responses (D). A 'list of risks requiring near-term responses' (C) requires…
Question
At the time the risk register is first prepared, it should contain all the following entries EXCEPT______________
Options
- ARoot causes of risk
- BStructure for describing risks
- CList of risks requiring near-term responses
- DList of potential responses
How the community answered
(60 responses)- A2% (1)
- B5% (3)
- C92% (55)
- D2% (1)
Explanation
When the risk register is first created during the Identify Risks process, it contains the structure for describing risks (B), root causes of risk (A), and a preliminary list of potential responses (D). A 'list of risks requiring near-term responses' (C) requires prioritization, which only happens after qualitative and/or quantitative risk analysis has been performed. That level of prioritization cannot exist at the initial identification stage, making C the correct exception.