PMI-RMP · Question #281
PMI-RMP Question #281: Real Exam Question with Answer & Explanation
The correct answer is C: List of risks requiring near-term responses. The primary outputs from identify risks are initial entries into the risk register. It ultimately contains outcomes of other risk management processes as they are conducted. As an output of identify risks, the risk register should contain a list of identified risks, a list of pot
Question
At the time the risk register is first prepared, it should contain all the following entries EXCEPT______________
Options
- ARoot causes of risk
- BStructure for describing risks
- CList of risks requiring near-term responses
- DList of potential responses
Explanation
The primary outputs from identify risks are initial entries into the risk register. It ultimately contains outcomes of other risk management processes as they are conducted. As an output of identify risks, the risk register should contain a list of identified risks, a list of potential responses, root causes that gave rise to the identified risks, and a structure for describing risks. [Planning] PMI®, PMBOK® Guide, 2013, 327
Topics
Community Discussion
No community discussion yet for this question.