PMI-RMP · Question #312

PMI-RMP Question #312: Real Exam Question with Answer & Explanation

The correct answer is D: Meetings and interviews with key stakeholders.. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

The risk manager examines the enterprise environmental factors to gain an understanding of the stakeholders' risk appetite. However, risk appetites are not determined. What is the best method a risk manager should use to initially define the stakeholders' risk appetite?

Options

  • AReview risk response strategies
  • BConduct SWOT analysis.
  • CWhat-if scenario.
  • DMeetings and interviews with key stakeholders.

Topics

#Risk Appetite#Stakeholder Engagement#Information Gathering#Risk Planning