PMIPMI
PMI-RMP · Question #233
PMI-RMP Question #233: Real Exam Question with Answer & Explanation
The correct answer is B: The level of detail should correspond with the priority ranking.. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Lisa is the project manager of the SQL project for her company. She has completed the risk response planning with her project team and is now ready to update the risk register to reflect the risk response. Which of the following statements best describes the level of detail Lisa should include with the risk responses she has created?
Options
- AThe level of detail is set by historical information.
- BThe level of detail should correspond with the priority ranking.
- CThe level of detail must define exactly the risk response for each identified risk.
- DThe level of detail is set of project risk governance.
Topics
#Risk Response Planning#Risk Register#Risk Priority#Level of Detail
Community Discussion
No community discussion yet for this question.