PMI-RMP · Question #233
Lisa is the project manager of the SQL project for her company. She has completed the risk response planning with her project team and is now ready to update the risk register to reflect the risk…
The correct answer is B. The level of detail should correspond with the priority ranking. The level of detail included in a risk response should be proportional to the risk's priority ranking, with high-priority risks receiving more thorough documentation.
Question
Lisa is the project manager of the SQL project for her company. She has completed the risk response planning with her project team and is now ready to update the risk register to reflect the risk response. Which of the following statements best describes the level of detail Lisa should include with the risk responses she has created?
Options
- AThe level of detail is set by historical information.
- BThe level of detail should correspond with the priority ranking.
- CThe level of detail must define exactly the risk response for each identified risk.
- DThe level of detail is set of project risk governance.
How the community answered
(31 responses)- A3% (1)
- B84% (26)
- C10% (3)
- D3% (1)
Why each option
The level of detail included in a risk response should be proportional to the risk's priority ranking, with high-priority risks receiving more thorough documentation.
Historical information is used to identify risks and estimate probability or impact, not to determine how much detail a response document requires.
High-priority risks pose the greatest threat to project objectives and therefore warrant detailed, actionable response plans, while low-priority risks may only need brief or general documentation. Scaling documentation detail to priority ensures that planning effort is allocated where it has the greatest impact. This approach is consistent with PMBOK guidance on efficient and proportionate risk response planning.
Requiring exhaustive detail for every identified risk regardless of its priority wastes resources and is not aligned with risk management best practices.
Project risk governance establishes the policies and framework for risk management overall but does not prescribe the documentation depth for individual risk responses.
Concept tested: Risk response documentation detail proportional to risk priority
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.