nerdexam
PMIPMI

PMI-RMP · Question #232

PMI-RMP Question #232: Real Exam Question with Answer & Explanation

The correct answer is A: Risks. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

You work as the project manager for Bluewell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decide, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project, what is likely to increase?

Options

  • ARisks
  • BCosts
  • CQuality control concerns
  • DHuman resource needs

Topics

#Fast-tracking#Schedule management#Risk increase#Project acceleration

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions