PMIPMI
PMI-RMP · Question #232
PMI-RMP Question #232: Real Exam Question with Answer & Explanation
The correct answer is A: Risks. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
You work as the project manager for Bluewell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decide, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project, what is likely to increase?
Options
- ARisks
- BCosts
- CQuality control concerns
- DHuman resource needs
Topics
#Fast-tracking#Schedule management#Risk increase#Project acceleration
Community Discussion
No community discussion yet for this question.