PMI-RMP · Question #232
You work as the project manager for Bluewell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decide, with your stakeholders' approval, to fast tr
The correct answer is A. Risks. Fast tracking overlaps activities that were planned to be sequential, which removes schedule buffers and directly increases project risk.
Question
You work as the project manager for Bluewell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decide, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project, what is likely to increase?
Options
- ARisks
- BCosts
- CQuality control concerns
- DHuman resource needs
How the community answered
(36 responses)- A83% (30)
- B11% (4)
- C3% (1)
- D3% (1)
Why each option
Fast tracking overlaps activities that were planned to be sequential, which removes schedule buffers and directly increases project risk.
Fast tracking is a schedule compression technique that runs originally sequential activities in parallel, eliminating the dependency protections built into the original plan. This overlap increases the likelihood of rework, coordination failures, and cascading errors, all of which raise overall project risk. Risk is the primary and accepted trade-off when fast tracking is chosen as a compression strategy.
Fast tracking does not inherently increase costs and is often used specifically to avoid schedule-driven cost overruns.
Quality control concerns are not the primary or most direct consequence of fast tracking activities.
Fast tracking applies existing resources to overlapping tasks and does not inherently require additional human resources.
Concept tested: Schedule compression via fast tracking and resulting risk increase
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.