PMI-RMP · Question #272
Joan is the project manager of the BTT project for her company. She has worked with her project to create risk responses for both positive and negative risk events within the project. As a result of…
The correct answer is D. Technical documentation. The Plan Risk Responses process requires updates to project documents including technical documentation when risk responses affect technical aspects of the project.
Question
Joan is the project manager of the BTT project for her company. She has worked with her project to create risk responses for both positive and negative risk events within the project. As a result of this process Joan needs to update the project document updates. She has updated the assumptions log as a result of the findings and risk responses, but what other documentation will need to be updated as an output of risk response planning?
Options
- AScope statement
- BLessons learned
- CRisk Breakdown Structure
- DTechnical documentation
How the community answered
(41 responses)- A12% (5)
- B5% (2)
- C7% (3)
- D76% (31)
Why each option
The Plan Risk Responses process requires updates to project documents including technical documentation when risk responses affect technical aspects of the project.
The scope statement is a component of the project scope baseline and is not listed as a standard project document update output from Plan Risk Responses.
Lessons learned are captured throughout the project but are not a specific output document update from the Plan Risk Responses process.
The Risk Breakdown Structure is a tool used in risk identification and planning, not a document updated as an output of risk response planning.
Technical documentation must be updated as a project document update when risk responses introduce changes to technical approaches, designs, or specifications. PMBOK identifies project document updates - including technical documentation - as a key output of the Plan Risk Responses process when response strategies alter how technical work will be executed.
Concept tested: Plan Risk Responses output - project document updates
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok