The correct answer is C: Planning meetings and analysis. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Fred is the project manager of a large project in his organization. Fred needs to begin planning the risk management plan with the project team and key stakeholders. Which plan risk management process tool and technique should Fred use to plan risk management?

Options

  • AVariance and trend analysis
  • BInformation gathering techniques
  • CPlanning meetings and analysis
  • DData gathering and representation techniques

Topics

#Risk Management Planning#Plan Risk Management Process#Planning Meetings#Tools and Techniques

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions