PMI-RMP · Question #271
PMI-RMP Question #271: Real Exam Question with Answer & Explanation
The correct answer is C: Planning meetings and analysis. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Fred is the project manager of a large project in his organization. Fred needs to begin planning the risk management plan with the project team and key stakeholders. Which plan risk management process tool and technique should Fred use to plan risk management?
Options
- AVariance and trend analysis
- BInformation gathering techniques
- CPlanning meetings and analysis
- DData gathering and representation techniques
Topics
#Risk Management Planning#Plan Risk Management Process#Planning Meetings#Tools and Techniques