PMI-RMP · Question #270
Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to…
The correct answer is B. Transference. Hiring a professional vendor to complete risky work and assume the associated danger is Transference. Transference shifts the negative risk impact and ownership to a third party (the vendor). It does not eliminate the risk-the risk still exists, but now it is the vendor's…
Question
Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?
Options
- AAcceptance
- BTransference
- CMitigation
- DAvoidance
How the community answered
(33 responses)- A12% (4)
- B79% (26)
- C3% (1)
- D6% (2)
Explanation
Hiring a professional vendor to complete risky work and assume the associated danger is Transference. Transference shifts the negative risk impact and ownership to a third party (the vendor). It does not eliminate the risk-the risk still exists, but now it is the vendor's responsibility. Acceptance (A) means doing nothing proactive. Mitigation (C) reduces probability or impact. Avoidance (D) eliminates the risk by changing the project plan entirely.