nerdexam
PMIPMI

PMI-RMP · Question #268

PMI-RMP Question #268: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #268. The question stem and answer options stay visible for context.

Risk Strategy and Planning

Question

Rex is the project manager of the BDF Project. This project will last for two years and has a budget of $2,345,000. Management has instructed Rex that the project must not go over budget as funds are very tight in the organization. During the project planning Rex and the project team discover a positive risk event to save $75,000. Rex wants to make certain that this risk event happens so which risk response method is most appropriate?

Options

  • AShare
  • BMitigation
  • CExploit
  • DEnhance

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Positive Risk Response#Exploit Strategy#Opportunity Management#Risk Response Planning
Full PMI-RMP PracticeBrowse All PMI-RMP Questions