PMI-RMP · Question #267

Melody is the project manager for her organization. She has created a risk response to conduct more tests on the software her project is creating. The identified risk that prompted this response was t

The correct answer is A. Mitigation. Conducting more tests on mission-critical software is a Mitigation response. Mitigation reduces the probability or impact of a risk-in this case, more testing reduces the probability that defects will make it into production. It does not eliminate the risk (Avoidance), transfer i

Risk Strategy and Planning

Question

Melody is the project manager for her organization. She has created a risk response to conduct more tests on the software her project is creating. The identified risk that prompted this response was that the software is mission-critical and must be flawless before it can be put into product. What type of a risk response has Melody used in this scenario?

Options

  • AMitigation
  • BEnhance
  • CTransference
  • DAvoidance

How the community answered

(29 responses)
  • A
    83% (24)
  • B
    3% (1)
  • C
    10% (3)
  • D
    3% (1)

Explanation

Conducting more tests on mission-critical software is a Mitigation response. Mitigation reduces the probability or impact of a risk-in this case, more testing reduces the probability that defects will make it into production. It does not eliminate the risk (Avoidance), transfer it to another party (Transference), or enhance a positive risk (Enhance). The goal is to bring the risk to an acceptable level before delivery.

Topics

#Risk response strategies#Threat mitigation#Project risk management