PMI-RMP Question #267: Real Exam Question with Answer & Explanation
The correct answer is A: Mitigation. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Melody is the project manager for her organization. She has created a risk response to conduct more tests on the software her project is creating. The identified risk that prompted this response was that the software is mission-critical and must be flawless before it can be put into product. What type of a risk response has Melody used in this scenario?
Options
- AMitigation
- BEnhance
- CTransference
- DAvoidance
Topics
#Risk response strategies#Threat mitigation#Project risk management