PMI-RMP · Question #267

PMI-RMP Question #267: Real Exam Question with Answer & Explanation

The correct answer is A: Mitigation. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Melody is the project manager for her organization. She has created a risk response to conduct more tests on the software her project is creating. The identified risk that prompted this response was that the software is mission-critical and must be flawless before it can be put into product. What type of a risk response has Melody used in this scenario?

Options

  • AMitigation
  • BEnhance
  • CTransference
  • DAvoidance

Topics

#Risk response strategies#Threat mitigation#Project risk management