Melody is the project manager for her organization. She has created a risk response to conduct more tests on the software her project is creating. The identified risk that prompted this response was…

The correct answer is A. Mitigation. Conducting more tests on mission-critical software is a Mitigation response. Mitigation reduces the probability or impact of a risk-in this case, more testing reduces the probability that defects will make it into production. It does not eliminate the risk (Avoidance), transfer…

Risk Strategy and Planning

Question

Melody is the project manager for her organization. She has created a risk response to conduct more tests on the software her project is creating. The identified risk that prompted this response was that the software is mission-critical and must be flawless before it can be put into product. What type of a risk response has Melody used in this scenario?

Options

  • AMitigation
  • BEnhance
  • CTransference
  • DAvoidance

How the community answered

(29 responses)
  • A
    83% (24)
  • B
    3% (1)
  • C
    10% (3)
  • D
    3% (1)

Explanation

Conducting more tests on mission-critical software is a Mitigation response. Mitigation reduces the probability or impact of a risk-in this case, more testing reduces the probability that defects will make it into production. It does not eliminate the risk (Avoidance), transfer it to another party (Transference), or enhance a positive risk (Enhance). The goal is to bring the risk to an acceptable level before delivery.

Topics

#Risk response strategies#Threat mitigation#Project risk management