nerdexam
PMI

PMI-RMP · Question #266

Which of the following processes involves choosing the alternative strategies, executing a contingency or fallback plan, taking corrective action, and modifying the project management plan?

The correct answer is A. Monitor and Control risk. Monitor and Control Risks is the process that involves choosing alternative strategies, executing contingency or fallback plans, taking corrective action, and modifying the project management plan as risks occur or conditions change. Configuration Management (B) controls product

Risk Monitoring and Reporting

Question

Which of the following processes involves choosing the alternative strategies, executing a contingency or fallback plan, taking corrective action, and modifying the project management plan?

Options

  • AMonitor and Control risk
  • BConfiguration Management
  • CIntegrated Change control
  • DScope Change control

How the community answered

(21 responses)
  • A
    90% (19)
  • C
    5% (1)
  • D
    5% (1)

Explanation

Monitor and Control Risks is the process that involves choosing alternative strategies, executing contingency or fallback plans, taking corrective action, and modifying the project management plan as risks occur or conditions change. Configuration Management (B) controls product specifications. Integrated Change Control (C) processes all change requests. Scope Change Control (D) manages scope-related changes only.

Topics

#Risk Monitoring and Control#Risk Response Execution#Contingency Planning#Corrective Actions

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice