PMIPMI
PMI-RMP · Question #80
PMI-RMP Question #80: Real Exam Question with Answer & Explanation
The correct answer is A: The low probability and low impact risks should be added to awatchlist for future monitoring.. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
Stephen is the project manager of the GBB project. He has worked with two subject matter experts and his project team to complete the risk assessment technique. There are approximately 47 risks that have a low probability and a low impact on the project. Which of the following answers best describes what Stephen should do with these risk events?
Options
- AThe low probability and low impact risks should be added to awatchlist for future monitoring.
- BBecause they are low probability and low impact, the risks can be dismissed.
- CThe low probability and low impact risks should be added to the risk register.
- DBecause they are low probability and low impact, Stephen should accept the risks.
Topics
#Risk assessment#Low probability low impact risks#Risk watchlist#Risk monitoring
Community Discussion
No community discussion yet for this question.