PMI-RMP · Question #80
Stephen is the project manager of the GBB project. He has worked with two subject matter experts and his project team to complete the risk assessment technique. There are approximately 47 risks that h
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #80. The question stem and answer options stay visible for context.
Question
Stephen is the project manager of the GBB project. He has worked with two subject matter experts and his project team to complete the risk assessment technique. There are approximately 47 risks that have a low probability and a low impact on the project. Which of the following answers best describes what Stephen should do with these risk events?
Options
- AThe low probability and low impact risks should be added to awatchlist for future monitoring.
- BBecause they are low probability and low impact, the risks can be dismissed.
- CThe low probability and low impact risks should be added to the risk register.
- DBecause they are low probability and low impact, Stephen should accept the risks.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.