PMI-RMP · Question #591

PMI-RMP Question #591: Real Exam Question with Answer & Explanation

The correct answer is D: Encourage the program team to assume risk ownership prior to delegation.. In a complex program, it is crucial for team members to assume ownership of risks before these are delegated. Encouraging the program team to assume risk ownership ensures that they are fully engaged and responsible for managing the risks assigned to them. This approach promotes

Risk Monitoring and Reporting

Question

While developing a risk management plan for a complex program in a metricized environment, a program management team is itemizing a response plan for each identified risk that appears in the risk register. What should the risk manager do to effectively monitor the risks?

Options

  • APresent the complicated nature of the program risk responses to the sponsor for proper advice.
  • BDetermine the workarounds for the program risks and allocate responsibilities to the team.
  • CAllow the most experienced program manager to handle the most critical program risks.
  • DEncourage the program team to assume risk ownership prior to delegation.

Explanation

In a complex program, it is crucial for team members to assume ownership of risks before these are delegated. Encouraging the program team to assume risk ownership ensures that they are fully engaged and responsible for managing the risks assigned to them. This approach promotes accountability and helps ensure that risks are actively managed throughout the program's lifecycle. PMI's guidelines on risk management emphasize the importance of assigning clear ownership of risks to ensure that they are effectively managed and that responsibilities are clearly understood by all team members.

Topics

#Risk Monitoring#Risk Ownership#Team Accountability#Risk Response Implementation