PMI-RMP · Question #296

Executing the risk response plan in order to react to risk events throughout the project is called:

The correct answer is B. Monitoring and control. Executing and overseeing risk response plans throughout the project lifecycle is part of the Monitor and Control Risks process.

Risk Monitoring and Reporting

Question

Executing the risk response plan in order to react to risk events throughout the project is called:

Options

  • AContingency planning.
  • BMonitoring and control.
  • CMitigation.
  • DLife cycle costing.

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    90% (27)
  • D
    7% (2)

Why each option

Executing and overseeing risk response plans throughout the project lifecycle is part of the Monitor and Control Risks process.

AContingency planning.

Contingency planning is the act of creating backup plans in advance, not the process of executing those plans when risk events occur.

BMonitoring and control.Correct

Monitor and Control Risks is the process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout project execution. It ensures that risk responses are actually carried out and that newly emerging risks are handled appropriately.

CMitigation.

Mitigation is a specific risk response strategy aimed at reducing the probability or impact of a threat, not the broader process of executing all risk responses.

DLife cycle costing.

Life cycle costing refers to evaluating total cost of ownership over a product's life span and is unrelated to risk response execution.

Concept tested: Monitor and Control Risks process execution

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk response execution#Risk monitoring#Risk control#Project execution