PMI-RMP · Question #297
In which of the following contract types does the buyer have the most cost risk?
The correct answer is A. Cost plus percentage of costs (CPPC). In a Cost Plus Percentage of Costs (CPPC) contract, the buyer bears the highest cost risk because the contractor's fee increases as costs increase, removing any incentive for cost control.
Question
In which of the following contract types does the buyer have the most cost risk?
Options
- ACost plus percentage of costs (CPPC)
- BCost plus fixed fee (CPFF)
- CCost plus award fee (CPAF)
- DCost plus incentive fee (CPIF)
How the community answered
(62 responses)- A92% (57)
- B2% (1)
- C5% (3)
- D2% (1)
Why each option
In a Cost Plus Percentage of Costs (CPPC) contract, the buyer bears the highest cost risk because the contractor's fee increases as costs increase, removing any incentive for cost control.
CPPC contracts reimburse the contractor for all allowable costs and pay an additional fee calculated as a percentage of those costs. This structure means the contractor actually earns more as costs rise, creating a perverse incentive. The buyer absorbs unlimited cost growth with no contractual mechanism to control it, making CPPC the riskiest contract type for the buyer.
CPFF reimburses costs plus a fixed fee that does not change regardless of actual costs, giving the contractor some incentive to control costs and limiting fee exposure for the buyer.
CPAF reimburses costs plus an award fee determined by buyer-assessed performance, which provides a performance incentive that partially protects the buyer.
CPIF reimburses costs plus an incentive fee tied to meeting target cost goals, which motivates the contractor to control costs and shares savings between both parties.
Concept tested: Contract types and buyer cost risk exposure
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.