nerdexam
PMIPMI

PMI-RMP · Question #298

PMI-RMP Question #298: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #298. The question stem and answer options stay visible for context.

Risk Strategy and Planning

Question

Giving a part of project work to a contractor is an example of:

Options

  • Arisk assumption
  • Brisk assignment
  • Crisk delegation
  • Drisk deflection
  • Erisk mitigation

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk response planning#Risk transfer#Contracting#Outsourcing
Full PMI-RMP PracticeBrowse All PMI-RMP Questions