PMI-RMP · Question #299

PMI-RMP Question #299: Real Exam Question with Answer & Explanation

The correct answer is A: mitigation. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Which is a valid response to negative risks?

Options

  • Amitigation
  • BEnhance
  • CExploit
  • DShare

Topics

#Risk response strategies#Negative risks#Threats#Mitigation