Which is a valid response to negative risks?

The correct answer is A. mitigation. Mitigation is a valid risk response strategy for negative risks (threats), aimed at reducing the probability or impact of the risk to an acceptable threshold.

Risk Strategy and Planning

Question

Which is a valid response to negative risks?

Options

  • Amitigation
  • BEnhance
  • CExploit
  • DShare

How the community answered

(24 responses)
  • A
    88% (21)
  • C
    8% (2)
  • D
    4% (1)

Why each option

Mitigation is a valid risk response strategy for negative risks (threats), aimed at reducing the probability or impact of the risk to an acceptable threshold.

AmitigationCorrect

Mitigation is one of the four standard responses to negative risks alongside Avoid, Transfer, and Accept. It involves taking proactive action to reduce the likelihood or consequence of a threat before it occurs, such as adopting less complex processes, conducting more tests, or choosing a more stable supplier.

BEnhance

Enhance is a response to positive risks (opportunities), used to increase the probability or impact of a beneficial event - not applicable to threats.

CExploit

Exploit is a response to positive risks (opportunities), used to ensure an opportunity definitely occurs - not applicable to negative risks.

DShare

Share is a response to positive risks (opportunities), used to allocate ownership of an opportunity to a third party best positioned to capture it - not applicable to threats.

Concept tested: Risk response strategies for threats vs. opportunities

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk response strategies#Negative risks#Threats#Mitigation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice