nerdexam
PMIPMI

PMI-RMP · Question #59

PMI-RMP Question #59: Real Exam Question with Answer & Explanation

The correct answer is D: Transference. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

You are the project manager for a construction project. The project involves casting of a column in a very narrow space. Because of lack of space, casting it is highly dangerous. High technical skill will be required for casting that column. You decide to hire a local expert team for casting that column. Which of the following types of risk response are you following?

Options

  • AAcceptance
  • BAvoidance
  • CMitigation
  • DTransference

Topics

#Risk Response Strategies#Risk Transference#Outsourcing Risk#Plan Risk Responses

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions