PMIPMI
PMI-RMP · Question #59
PMI-RMP Question #59: Real Exam Question with Answer & Explanation
The correct answer is D: Transference. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
You are the project manager for a construction project. The project involves casting of a column in a very narrow space. Because of lack of space, casting it is highly dangerous. High technical skill will be required for casting that column. You decide to hire a local expert team for casting that column. Which of the following types of risk response are you following?
Options
- AAcceptance
- BAvoidance
- CMitigation
- DTransference
Topics
#Risk Response Strategies#Risk Transference#Outsourcing Risk#Plan Risk Responses
Community Discussion
No community discussion yet for this question.