nerdexam
PMIPMI

PMI-RMP · Question #58

PMI-RMP Question #58: Real Exam Question with Answer & Explanation

The correct answer is C: Risk distributions within the project schedule. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

You work as a project manager for TechSoft Inc. You, the project team, and the key project stakeholders have completed a round of quantitative risk analysis. You now need to update the risk register with your findings so that you can communicate the risk results to the project stakeholders - including management. You will need to update all of the following information except for which one?

Options

  • AProbabilistic analysis of the project
  • BProbability of achieving cost and time objectives
  • CRisk distributions within the project schedule
  • DTrends in quantitative risk analysis

Topics

#Quantitative Risk Analysis#Risk Register#Risk Communication#Project Outcomes

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions