PMIPMI
PMI-RMP · Question #58
PMI-RMP Question #58: Real Exam Question with Answer & Explanation
The correct answer is C: Risk distributions within the project schedule. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
You work as a project manager for TechSoft Inc. You, the project team, and the key project stakeholders have completed a round of quantitative risk analysis. You now need to update the risk register with your findings so that you can communicate the risk results to the project stakeholders - including management. You will need to update all of the following information except for which one?
Options
- AProbabilistic analysis of the project
- BProbability of achieving cost and time objectives
- CRisk distributions within the project schedule
- DTrends in quantitative risk analysis
Topics
#Quantitative Risk Analysis#Risk Register#Risk Communication#Project Outcomes
Community Discussion
No community discussion yet for this question.