nerdexam
PMIPMI

PMI-RMP · Question #629

PMI-RMP Question #629: Real Exam Question with Answer & Explanation

The correct answer is B: Residual risk. Residual risks are those that remain after implementing risk response strategies. In this scenario, the primary risk is a major power outage that could lead to the failure of the digital platform hosting the new product database. The financial institution has mitigated this risk

Risk Monitoring and Reporting

Question

A financial institution is creating a new product database tor their clients. The project sponsor of this project is concerned about failure of the digital platform that hosts the database. The risk manager states that this risk will only occur if there is a major power outage; however, the financial institution has back-up power generators in place. What type of risk is being referred to here?

Options

  • AMajor risk
  • BResidual risk
  • CSecondary risk
  • DEnvironment risk

Explanation

Residual risks are those that remain after implementing risk response strategies. In this scenario, the primary risk is a major power outage that could lead to the failure of the digital platform hosting the new product database. The financial institution has mitigated this risk by installing backup power generators. However, the possibility of a power outage still exists, and the effectiveness of the backup generators cannot be guaranteed with absolute certainty. Therefore, the remaining risk, despite the mitigation measures, is classified as residual risk.

Topics

#Residual Risk#Risk Responses#Risk Monitoring#Risk Identification

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions