nerdexam
PMI

PMI-RMP · Question #628

A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and imp

The correct answer is A. Work with the project team to conduct a decision tree analysis for each risk or set of related risks. B. Calculate the expected monetary value (EMV) of each risk and use these outputs to inform and E. Focus attention and resources on identified risks with the highest potential to impact the project.. Three actions are correct: (A) Decision tree analysis evaluates choices and their associated outcomes, helping the team understand which risk responses are viable and what resources different response paths would require. (B) Calculating Expected Monetary Value (EMV) quantifies e

Perform Targeted Risk Analysis

Question

A risk manager for a new product development project has worked diligently with stakeholders and the project team to identify and document risks. These project risks vary widely in probability and impact. Which three actions should the risk manager take to inform the identification of resource requirements for individual risk responses? (Choose 3).

Options

  • AWork with the project team to conduct a decision tree analysis for each risk or set of related risks.
  • BCalculate the expected monetary value (EMV) of each risk and use these outputs to inform and
  • CConduct a Monte Carlo simul-ation to understand the probabilities of various risk outcomes.
  • DUse the risk breakdown structure (RBS) to calculate the total cost of mitigating all risks and ensure
  • EFocus attention and resources on identified risks with the highest potential to impact the project.

How the community answered

(34 responses)
  • A
    71% (24)
  • C
    9% (3)
  • D
    21% (7)

Explanation

Three actions are correct: (A) Decision tree analysis evaluates choices and their associated outcomes, helping the team understand which risk responses are viable and what resources different response paths would require. (B) Calculating Expected Monetary Value (EMV) quantifies each risk in financial terms (probability × impact), providing a data-driven basis for determining how much resource investment is justified per risk response. (E) Focusing resources on risks with the highest potential impact is a core risk prioritization principle-resource allocation should be weighted toward risks that matter most to project outcomes. Option C (Monte Carlo simulation) provides probability distributions for overall project outcomes but is less suited to resource allocation for individual risk responses. Option D is incorrect because the RBS is a categorization tool, not a cost-calculation mechanism for mitigation resources.

Topics

#Quantitative Risk Analysis#Risk Response Planning#Risk Prioritization#Resource Allocation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice