PMI-RMP · Question #630
During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800 000. Wh
The correct answer is A. Sensitivity analysis. Sensitivity analysis is a quantitative risk analysis technique used to determine how variations in individual project risks affect project objectives, such as cost, schedule, or performance. By analyzing the sensitivity of these variables, the project team can identify which risk
Question
During a meeting with a project team, a project manager asks a risk manager to determine the risk events that could potentially have the most impact on a 2-year project with a budget of US$800 000. Which approach should the risk manager suggest the project manager take?
Options
- ASensitivity analysis
- Bsimul-ation analysis
- CMonte Carlo simul-ation
- DQuantitative analysis
How the community answered
(48 responses)- A73% (35)
- B4% (2)
- C15% (7)
- D8% (4)
Explanation
Sensitivity analysis is a quantitative risk analysis technique used to determine how variations in individual project risks affect project objectives, such as cost, schedule, or performance. By analyzing the sensitivity of these variables, the project team can identify which risks have the most significant potential impact on the project. This information is crucial for prioritizing risk responses and allocating resources effectively.
Topics
Community Discussion
No community discussion yet for this question.