PMI-RMP · Question #495

PMI-RMP Question #495: Real Exam Question with Answer & Explanation

The correct answer is B: US$72.000. The project risk exposure is the total amount of potential loss that the project may incur due to the occurrence of identified risks. It can be calculated by multiplying the probability and impact of each risk and then summing up the results. In this case, the project risk exposu

Perform Targeted Risk Analysis

Question

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3. What is the current project risk exposure?

Options

  • AUS$18,000
  • BUS$72.000
  • CUS$30,000
  • DUS$48,000

Explanation

The project risk exposure is the total amount of potential loss that the project may incur due to the occurrence of identified risks. It can be calculated by multiplying the probability and impact of each risk and then summing up the results. In this case, the project risk exposure can be computed as follows: Risk A: 0.6 x 50,000 = 30,000 Risk B: 0.3 x 60,000 = 18,000 Total: 30,000 + 18,000 = 48,000 However, this calculation does not take into account the percentage of completion of the project, which is 40%. Since the project is already 40% complete, the remaining 60% of the project is exposed to the identified risks. Therefore, the current project risk exposure should be adjusted by multiplying the total risk exposure by 0.6. This gives the following result: Current project risk exposure: 48,000 x 0.6 = 28,800

Topics

#Risk Exposure#Expected Monetary Value (EMV)#Quantitative Risk Analysis#Risk Response Evaluation