PMI-RMP · Question #495

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 a

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #495. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3. What is the current project risk exposure?

Options

  • AUS$18,000
  • BUS$72.000
  • CUS$30,000
  • DUS$48,000

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Exposure#Expected Monetary Value (EMV)#Quantitative Risk Analysis#Risk Response Evaluation