PMI-RMP · Question #35
PMI-RMP Question #35: Real Exam Question with Answer & Explanation
The correct answer is C: Configuration management system. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
Henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project, has introduced a scope change request for additional deliverables as part of the project work. What component of the change control system would review the proposed changes' impact on the features and functions of the project's product?
Options
- AScope change control system
- BCost change control system
- CConfiguration management system
- DIntegrated change control
Topics
#Configuration management#Change control#Product scope#Integrated change control