Henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project, has…
The correct answer is C. Configuration management system. The configuration management system focuses specifically on the product's features, functions, and physical/functional characteristics. When a scope change is proposed, the configuration management system reviews how that change affects the product's specifications and…
Question
Henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project, has introduced a scope change request for additional deliverables as part of the project work. What component of the change control system would review the proposed changes' impact on the features and functions of the project's product?
Options
- AScope change control system
- BCost change control system
- CConfiguration management system
- DIntegrated change control
How the community answered
(45 responses)- A2% (1)
- B4% (2)
- C82% (37)
- D11% (5)
Explanation
The configuration management system focuses specifically on the product's features, functions, and physical/functional characteristics. When a scope change is proposed, the configuration management system reviews how that change affects the product's specifications and baseline. Integrated change control (D) is the broader process that coordinates all changes across the project, but the specific component that evaluates product feature/function impact is configuration management. The scope change control system tracks scope changes, and the cost change control system tracks cost impacts.