The correct answer is C: Configuration management system. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

Henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project, has introduced a scope change request for additional deliverables as part of the project work. What component of the change control system would review the proposed changes' impact on the features and functions of the project's product?

Options

  • AScope change control system
  • BCost change control system
  • CConfiguration management system
  • DIntegrated change control

Topics

#Configuration management#Change control#Product scope#Integrated change control

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions