nerdexam
PMIPMI

PMI-RMP · Question #34

PMI-RMP Question #34: Real Exam Question with Answer & Explanation

The correct answer is C: Yes, change requests can be recommended for corrective actions for contingency plans.. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Ruth is the project manager of ISFH project for her company. This project is forty percent complete and it appears that some risk events are going to happen in the project that will have an adverse affect on the project. Ruth creates a change request regarding the risks. Is this a valid response?

Options

  • ANo, change requests should not address risks, only risk response strategies should be issued.
  • BNo, change requests should not address pending risks, but only scope changes.
  • CYes, change requests can be recommended for corrective actions for contingency plans.
  • DYes, change requests can ask for additional funds to pay for the risk impact.

Topics

#Change Requests#Risk Response#Corrective Actions#Contingency Plans

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions