PMI
PMI-RMP · Question #34
Ruth is the project manager of ISFH project for her company. This project is forty percent complete and it appears that some risk events are going to happen in the project that will have an adverse af
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #34. The question stem and answer options stay visible for context.
Risk Monitoring and Reporting
Question
Ruth is the project manager of ISFH project for her company. This project is forty percent complete and it appears that some risk events are going to happen in the project that will have an adverse affect on the project. Ruth creates a change request regarding the risks. Is this a valid response?
Options
- ANo, change requests should not address risks, only risk response strategies should be issued.
- BNo, change requests should not address pending risks, but only scope changes.
- CYes, change requests can be recommended for corrective actions for contingency plans.
- DYes, change requests can ask for additional funds to pay for the risk impact.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Requests#Risk Response#Corrective Actions#Contingency Plans