PMI-RMP · Question #33
PMI-RMP Question #33: Real Exam Question with Answer & Explanation
The correct answer is B: Perform Quantitative Risk Analysis. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
Which of the following processes is described in the statement below? "This is the process of numerically analyzing the effect of identified risks on overall project objectives."
Options
- AIdentify Risks
- BPerform Quantitative Risk Analysis
- CMonitor and Control Risks
- DPerform Qualitative Risk Analysis
Topics
#Quantitative Risk Analysis#Risk Analysis#Project Risk Management#Numerical Analysis