PMIPMI
PMI-RMP · Question #471
PMI-RMP Question #471: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #471. The question stem and answer options stay visible for context.
Perform Targeted Risk Analysis
Question
A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model. What is an effect of adding the correlation to the model?
Options
- AAllows more risks to be included in the model.
- BReduces the project completion duration.
- CIncreases the standard deviation of the model.
- DIncreases the probability of correlated activities finishing on time.
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Monte Carlo Simulation#Schedule Risk Analysis#Correlation#Standard Deviation