PMI-RMP · Question #472
The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager no
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #472. The question stem and answer options stay visible for context.
Question
The project manager for project X was expecting the mobilization of critical equipment from another project, project Y. However, a day before the mobilization was scheduled, another project manager notifies project X's project manager that the equipment would not be available for at least another month due to delayed activities for project Y. This has jeopardized meeting a critical milestone for project X. How should project X's project manager avoid this situation in the future?
Options
- APrepare a contingency response plan to implement when delays occur
- BAsk the other project manager to officially confirm the new date in writing
- CRequest that the other project manager be added to relevant reports
- DRequest that the other project manager inform if any additional delays are expected
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.