PMI-RMP · Question #457
A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide
The correct answer is A. Project contracts B. Lessons learned registers from analogous projects D. Risk management plan. The project manager should consult or review project contracts, lessons learned registers from analogous projects, and the risk management plan to develop an effective risk planning for the According to the PMBOK?Guide, the risk management plan is one of the key inputs for the pl
Question
A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project. What three artifacts should the project manager consult or review during this process? (Choose three.)
Options
- AProject contracts
- BLessons learned registers from analogous projects
- CRisk register
- DRisk management plan
- ECode of regulations
How the community answered
(22 responses)- A82% (18)
- C5% (1)
- E14% (3)
Explanation
The project manager should consult or review project contracts, lessons learned registers from analogous projects, and the risk management plan to develop an effective risk planning for the According to the PMBOK?Guide, the risk management plan is one of the key inputs for the plan risk management process, which is the first process in the project risk management knowledge area. The risk management plan describes how risk management activities will be structured and performed throughout the project. It includes information such as the methodology, roles and responsibilities, budget, timing, risk categories, definitions of risk probability and impact, probability and impact matrix, revised stakeholders' risk tolerances, reporting formats, and tracking (page 409). The project contracts are also an important input for the plan risk management process, as they may contain terms and conditions that can create or affect various project risks. For example, contracts may include clauses related to penalties, incentives, warranties, intellectual property rights, termination, force majeure, arbitration, indemnification, etc. The project manager should review the project contracts to identify any potential sources of risk and plan appropriate responses (page 410). The lessons learned registers from analogous projects are another valuable input for the plan risk management process, as they provide historical information and knowledge that can help the project manager identify and analyze risks, as well as plan risk responses. The lessons learned registers may contain information such as the risks that occurred, the root causes of the risks, the risk triggers, the effectiveness of the risk responses, the residual and secondary risks, the risk owners, the risk ratings, the risk trends, etc. The project manager should consult the lessons learned registers from similar or comparable projects to learn from past experiences and avoid repeating mistakes (page 411).