PMIPMI
PMI-RMP · Question #456
PMI-RMP Question #456: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #456. The question stem and answer options stay visible for context.
Risk Monitoring and Reporting
Question
The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path. What recommendation should the risk manager make to the project manager?
Options
- AAdd more float to the key activity
- BAdd more contingency to the project
- CReview the plans for the key activity
- DIncrease the budget for the key activity
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Critical Path Analysis#Monte Carlo Simulation#Schedule Risk#Risk Monitoring and Control