nerdexam
PMI

PMI-RMP · Question #456

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path. What recommendation should the

The correct answer is C. Review the plans for the key activity. When a Monte Carlo simulation reveals that a key activity has moved onto the critical path (meaning it now has zero float), the immediate and most appropriate response is to review the plans for that activity. This review will help determine why the activity migrated to the criti

Risk Monitoring and Reporting

Question

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path. What recommendation should the risk manager make to the project manager?

Options

  • AAdd more float to the key activity
  • BAdd more contingency to the project
  • CReview the plans for the key activity
  • DIncrease the budget for the key activity

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    5% (2)
  • C
    74% (28)
  • D
    16% (6)

Explanation

When a Monte Carlo simulation reveals that a key activity has moved onto the critical path (meaning it now has zero float), the immediate and most appropriate response is to review the plans for that activity. This review will help determine why the activity migrated to the critical path - whether due to scope changes, resource constraints, predecessor delays, or new risks - and what corrective options exist. Option A is incorrect because float is a calculated result of schedule logic, not something manually added. Option B (adding contingency) and D (increasing budget) are premature responses that address cost rather than the root cause of the schedule risk. Reviewing the plans first provides the information needed to make any of those other decisions intelligently.

Topics

#Critical Path Analysis#Monte Carlo Simulation#Schedule Risk#Risk Monitoring and Control

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice