PMI-RMP · Question #523
PMI-RMP Question #523: Real Exam Question with Answer & Explanation
The correct answer is B: Plan responses for the new risk.. The risk manager should first update the risk register with the new risk identified by the vendor. This will help in keeping track of all the risks associated with the project and facilitate the subsequent planning and management of the risks. The risk manager should update the n
Question
During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk. What should the risk manager do first?
Options
- AUpdate the new risk in the risk register.
- BPlan responses for the new risk.
- CPassively accept the new risk.
- DAdd the new risk to the watch list.
Explanation
The risk manager should first update the risk register with the new risk identified by the vendor. This will help in keeping track of all the risks associated with the project and facilitate the subsequent planning and management of the risks. The risk manager should update the new risk in the risk register, which is a project document that records the details of all identified risks, including their description, category, cause, probability, impact, and response strategy. Updating the risk register is the first step to acknowledge the existence of the new risk and to document its characteristics and potential effects on the project objectives. The risk register can then be used as an input for the Plan Risk Responses process, where the risk manager can develop appropriate actions to address the new risk.
Topics