The correct answer is B: Aligning to project constraints and priorities.. To ensure an effective risk management plan, the risk manager needs to consider aligning the plan to project constraints and priorities and obtaining stakeholder acceptance, as these factors will help ensure that the plan is relevant and supported by the project team and stakehol
Question
A risk manager of a major project facilitates a meeting to develop the risk management plan. What two factors does the risk manager need to consider to ensure an effective risk management plan is developed? (Choose two.)
Options
- AApplying modern risk management techniques.
- BAligning to project constraints and priorities.
- CEnsuring risk response strategies mitigate all risks.
- DMinimizing implementation costs.
- EObtaining stakeholder acceptance
Explanation
To ensure an effective risk management plan, the risk manager needs to consider aligning the plan to project constraints and priorities and obtaining stakeholder acceptance, as these factors will help ensure that the plan is relevant and supported by the project team and stakeholders. According to the PMI-RMP Handbook, the risk management plan is a document that describes how risk management activities will be structured and performed on the project. It is one of the main outputs of the Plan Risk Management process. The risk management plan should consider the following factors to ensure its effectiveness: Aligning to project constraints and priorities: The risk management plan should be aligned with the project objectives, scope, schedule, cost, quality, resources, and stakeholder expectations. It should also reflect the project's risk appetite, tolerance, and threshold levels, which indicate the degree of uncertainty that the project can accept. The risk management plan should prioritize the risk management activities based on the project's critical success factors and key performance indicators. Obtaining stakeholder acceptance: The risk management plan should be developed with the involvement and input of key stakeholders, such as the project sponsor, customer, team members, subject matter experts, and other relevant parties. The risk management plan should be communicated and approved by the stakeholders to ensure their commitment and support for the risk management process. The risk management plan should also define the roles and responsibilities of the stakeholders in risk management, as well as the reporting and escalation