PMI-RMP · Question #417
The risk manager is prioritizing risks based on the potential impact to cost and schedule and identifies the following 4 risks: Risk 1 has a US$500,000 potential cost increase, and a 60 day potential
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #417. The question stem and answer options stay visible for context.
Question
The risk manager is prioritizing risks based on the potential impact to cost and schedule and identifies the following 4 risks:
Risk 1 has a US$500,000 potential cost increase, and a 60 day potential schedule slippage, with a 25% probability of occurring Risk 2 has a US$200,000 potential cost increase, and a 20 day potential schedule slippage, with a 60% probability of occurring Risk 3 has a US$1,200,000 potential cost increase, and a 90 day potential schedule slippage, with a 10% probability of occurring Risk 4 has @ US$600,000 potential cost increase, and a 70 day potential schedule slippage, with a 20% probability of occurring Using expected monetary value calculation, which risk has the greatest potential impact to cost and schedule?
Options
- ARisk 1
- BRisk 2
- CRisk 3
- DRisk 4
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.