PMI-RMP · Question #417
PMI-RMP Question #417: Real Exam Question with Answer & Explanation
The correct answer is A: Risk 1. See the full explanation below for the reasoning.
Question
The risk manager is prioritizing risks based on the potential impact to cost and schedule and identifies the following 4 risks: Risk 1 has a US$500,000 potential cost increase, and a 60 day potential schedule slippage, with a 25% probability of occurring Risk 2 has a US$200,000 potential cost increase, and a 20 day potential schedule slippage, with a 60% probability of occurring Risk 3 has a US$1,200,000 potential cost increase, and a 90 day potential schedule slippage, with a 10% probability of occurring Risk 4 has @ US$600,000 potential cost increase, and a 70 day potential schedule slippage, with a 20% probability of occurring Using expected monetary value calculation, which risk has the greatest potential impact to cost and schedule?
Options
- ARisk 1
- BRisk 2
- CRisk 3
- DRisk 4
Topics
Community Discussion
No community discussion yet for this question.