nerdexam
PMI

PMI-RMP · Question #417

The risk manager is prioritizing risks based on the potential impact to cost and schedule and identifies the following 4 risks: Risk 1 has a US$500,000 potential cost increase, and a 60 day potential

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #417. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

The risk manager is prioritizing risks based on the potential impact to cost and schedule and identifies the following 4 risks:

Risk 1 has a US$500,000 potential cost increase, and a 60 day potential schedule slippage, with a 25% probability of occurring Risk 2 has a US$200,000 potential cost increase, and a 20 day potential schedule slippage, with a 60% probability of occurring Risk 3 has a US$1,200,000 potential cost increase, and a 90 day potential schedule slippage, with a 10% probability of occurring Risk 4 has @ US$600,000 potential cost increase, and a 70 day potential schedule slippage, with a 20% probability of occurring Using expected monetary value calculation, which risk has the greatest potential impact to cost and schedule?

Options

  • ARisk 1
  • BRisk 2
  • CRisk 3
  • DRisk 4

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Expected Monetary Value (EMV)#Quantitative Risk Analysis#Risk Prioritization#Cost-Benefit Analysis
Full PMI-RMP Practice