nerdexam
PMI

PMI-RMP · Question #252

You are a risk auditor for your company. You are reviewing the contract types a project manager has used in her project. Of the following, which contract type has the most risk for the project manager

The correct answer is A. Cost plus percentage of costs. Cost plus percentage of costs (CPPC) is the riskiest contract for the buyer because the seller's fee grows as costs increase, creating no incentive to control spending.

Perform Targeted Risk Analysis

Question

You are a risk auditor for your company. You are reviewing the contract types a project manager has used in her project. Of the following, which contract type has the most risk for the project manager as a buyer?

Options

  • ACost plus percentage of costs
  • BTime and material
  • CCost plus incentive fee
  • DFixed-price, incentive fee

How the community answered

(61 responses)
  • A
    90% (55)
  • B
    7% (4)
  • C
    2% (1)
  • D
    2% (1)

Why each option

Cost plus percentage of costs (CPPC) is the riskiest contract for the buyer because the seller's fee grows as costs increase, creating no incentive to control spending.

ACost plus percentage of costsCorrect

In a CPPC contract, the seller is reimbursed for all allowable costs and also receives a fee calculated as a percentage of those costs, meaning higher costs directly produce a higher fee for the seller. This structure gives the seller a financial incentive to allow or even inflate costs, exposing the buyer to unlimited and uncontrolled cost risk. No other standard contract type creates this perverse dynamic for the buyer.

BTime and material

Time and material contracts carry some cost risk for the buyer but are typically capped and controlled through defined labor rates and material limits.

CCost plus incentive fee

Cost plus incentive fee contracts include a performance-based incentive structure that motivates the seller to control costs, reducing buyer exposure compared to CPPC.

DFixed-price, incentive fee

Fixed-price contracts transfer the majority of cost risk to the seller, making them the least risky option for the buyer.

Concept tested: Contract type risk allocation for project buyers

Topics

#Contract Types#Procurement Risk#Buyer Risk#Risk Allocation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice