nerdexam
PMIPMI

PMI-RMP · Question #252

PMI-RMP Question #252: Real Exam Question with Answer & Explanation

The correct answer is A: Cost plus percentage of costs. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

You are a risk auditor for your company. You are reviewing the contract types a project manager has used in her project. Of the following, which contract type has the most risk for the project manager as a buyer?

Options

  • ACost plus percentage of costs
  • BTime and material
  • CCost plus incentive fee
  • DFixed-price, incentive fee

Topics

#Contract Types#Procurement Risk#Buyer Risk#Risk Allocation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions