PMIPMI
PMI-RMP · Question #252
PMI-RMP Question #252: Real Exam Question with Answer & Explanation
The correct answer is A: Cost plus percentage of costs. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
You are a risk auditor for your company. You are reviewing the contract types a project manager has used in her project. Of the following, which contract type has the most risk for the project manager as a buyer?
Options
- ACost plus percentage of costs
- BTime and material
- CCost plus incentive fee
- DFixed-price, incentive fee
Topics
#Contract Types#Procurement Risk#Buyer Risk#Risk Allocation
Community Discussion
No community discussion yet for this question.