PMIPMI
PMI-RMP · Question #253
PMI-RMP Question #253: Real Exam Question with Answer & Explanation
The correct answer is A: Acceptance. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Jane is the project manager of the GBB project for her company. In the current project a vendor has offered the project a ten percent discount based if they will order 100 units for the project. It is possible that the GBB Project may need the 100 units, but the cost of the units is not a top priority for the project. Jane documents the offer and tells the vendor that they will keep the offer in mind and continue with the project as planned. What risk response has been given in this project?
Options
- AAcceptance
- BEnhance
- CExploiting
- DSharing
Topics
#Risk response strategies#Opportunity management#Acceptance (risk response)#Positive risk
Community Discussion
No community discussion yet for this question.