nerdexam
PMIPMI

PMI-RMP · Question #254

PMI-RMP Question #254: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #254. The question stem and answer options stay visible for context.

Perform Targeted Risk Analysis

Question

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?

Options

  • A$142,000
  • B$41,750
  • C$23,750
  • D$232,000

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Contingency Reserve#Expected Monetary Value (EMV)#Quantitative Risk Analysis#Risk Budgeting
Full PMI-RMP PracticeBrowse All PMI-RMP Questions