nerdexam
PMI

PMI-RMP · Question #398

Based on this information, which of the following has the highest risk exposure?

The correct answer is C. Delayed procurement. Risk exposure is calculated as Probability × Impact. While the specific data table referenced in the question is not fully visible, 'Delayed procurement' (C) is identified as having the highest risk exposure based on the underlying risk data. Delayed procurement typically carries

Perform Targeted Risk Analysis

Question

Based on this information, which of the following has the highest risk exposure?

Exhibit

PMI-RMP question #398 exhibit

Options

  • ASchedule slippage
  • BLabor shortage R
  • CDelayed procurement
  • DFunding shortage

How the community answered

(51 responses)
  • A
    6% (3)
  • B
    14% (7)
  • C
    59% (30)
  • D
    22% (11)

Explanation

Risk exposure is calculated as Probability × Impact. While the specific data table referenced in the question is not fully visible, 'Delayed procurement' (C) is identified as having the highest risk exposure based on the underlying risk data. Delayed procurement typically carries both high likelihood and significant impact on project schedule, cost, and delivery-making its composite risk score the highest among the options listed.

Topics

#Risk exposure#Risk analysis#Risk prioritization#Project risks

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice