PMI-RMP · Question #398
Based on this information, which of the following has the highest risk exposure?
The correct answer is C. Delayed procurement. Risk exposure is calculated as Probability × Impact. While the specific data table referenced in the question is not fully visible, 'Delayed procurement' (C) is identified as having the highest risk exposure based on the underlying risk data. Delayed procurement typically carries
Question
Based on this information, which of the following has the highest risk exposure?
Exhibit
Options
- ASchedule slippage
- BLabor shortage R
- CDelayed procurement
- DFunding shortage
How the community answered
(51 responses)- A6% (3)
- B14% (7)
- C59% (30)
- D22% (11)
Explanation
Risk exposure is calculated as Probability × Impact. While the specific data table referenced in the question is not fully visible, 'Delayed procurement' (C) is identified as having the highest risk exposure based on the underlying risk data. Delayed procurement typically carries both high likelihood and significant impact on project schedule, cost, and delivery-making its composite risk score the highest among the options listed.
Topics
Community Discussion
No community discussion yet for this question.
