nerdexam
PMIPMI

PMI-RMP · Question #397

PMI-RMP Question #397: Real Exam Question with Answer & Explanation

The correct answer is C: Develop a risk management plan and present it to the sponsor.. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

The project manager needs to create a risk management plan for a high risk project, but the company's senior management does not see value in spending time documenting major risks instead of leading the project. What is the most appropriate action for the project manager to take first?

Options

  • ADevelop a risk register and present it to the senior management
  • BHire a risk consultant to identity the major risks.
  • CDevelop a risk management plan and present it to the sponsor.
  • DDocument all identified risks.

Topics

#Risk Management Planning#Stakeholder Engagement#Sponsor Management#Overcoming Resistance

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions