PMI-RMP · Question #32
During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?
The correct answer is A. Cost of the project. Risk urgency assessment evaluates how quickly a risk must be addressed. Its indicators include: risk rating (probability × impact score), warning signs or triggers that indicate a risk is imminent, and symptoms that suggest a risk event may already be developing. The overall…
Question
During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?
Options
- ACost of the project
- BRisk rating
- CWarning signs
- DSymptoms
How the community answered
(39 responses)- A95% (37)
- B3% (1)
- C3% (1)
Explanation
Risk urgency assessment evaluates how quickly a risk must be addressed. Its indicators include: risk rating (probability × impact score), warning signs or triggers that indicate a risk is imminent, and symptoms that suggest a risk event may already be developing. The overall cost of the project is a high-level project parameter, not an indicator of how urgent or prioritized an individual risk is. It does not help determine the relative priority or timing of a specific risk response.