PMIPMI
PMI-RMP · Question #31
PMI-RMP Question #31: Real Exam Question with Answer & Explanation
The correct answer is C: Sharing. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
You work as a project manager for BlueWell Inc. You are working with your team members on the risk responses in the project. Which risk response will likely cause a project to use the procurement processes?
Options
- AExploiting
- BMitigation
- CSharing
- DAcceptance
Topics
#Risk responses#Opportunity management#Risk sharing#Procurement processes
Community Discussion
No community discussion yet for this question.