nerdexam
PMIPMI

PMI-RMP · Question #30

PMI-RMP Question #30: Real Exam Question with Answer & Explanation

The correct answer is C: Transference. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this?

Options

  • AExploit
  • BMitigation
  • CTransference
  • DAvoidance

Topics

#Risk response strategies#Risk transference#Outsourcing#Risk management

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions