PMIPMI
PMI-RMP · Question #30
PMI-RMP Question #30: Real Exam Question with Answer & Explanation
The correct answer is C: Transference. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this?
Options
- AExploit
- BMitigation
- CTransference
- DAvoidance
Topics
#Risk response strategies#Risk transference#Outsourcing#Risk management
Community Discussion
No community discussion yet for this question.