PMI-RMP · Question #29
There are four inputs to the Monitoring and Controlling Project Risks process. Which one of the following will NOT help you, the project manager, to prepare for risk monitoring and controlling?
The correct answer is D. Change requests. Change Requests are an OUTPUT of the Monitor and Control Risks process, not an input. They result from risk monitoring activities when corrective or preventive actions are needed. The four standard inputs to Monitor and Control Risks are: the Risk Register (C), which contains…
Question
There are four inputs to the Monitoring and Controlling Project Risks process. Which one of the following will NOT help you, the project manager, to prepare for risk monitoring and controlling?
Options
- AWork Performance Information
- BProject management plan
- CRisk register
- DChange requests
How the community answered
(40 responses)- A5% (2)
- B3% (1)
- C3% (1)
- D90% (36)
Explanation
Change Requests are an OUTPUT of the Monitor and Control Risks process, not an input. They result from risk monitoring activities when corrective or preventive actions are needed. The four standard inputs to Monitor and Control Risks are: the Risk Register (C), which contains identified risks and response plans; the Project Management Plan (B), which includes the risk management plan; Work Performance Information (A), which provides data on actual project status; and Work Performance Reports. Since Change Requests are generated by this process, they cannot also be used to prepare for it.