PMIPMI
PMI-RMP · Question #29
PMI-RMP Question #29: Real Exam Question with Answer & Explanation
The correct answer is D: Change requests. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
There are four inputs to the Monitoring and Controlling Project Risks process. Which one of the following will NOT help you, the project manager, to prepare for risk monitoring and controlling?
Options
- AWork Performance Information
- BProject management plan
- CRisk register
- DChange requests
Topics
#Risk Monitoring#PMBOK Processes#Process Inputs#Risk Control
Community Discussion
No community discussion yet for this question.