You are the project manager for BlueWell Inc. Your current project is a high priority and high profile project within your organization. You want to identify the project stakeholders that will have…

The correct answer is A. Stakeholder power/interest grid. The power/interest grid maps stakeholders on two axes: level of authority (power) and level of concern about project outcomes (interest). It directly answers the need to identify who has the most power relative to their interest, which guides communication and engagement…

Stakeholder Engagement

Question

You are the project manager for BlueWell Inc. Your current project is a high priority and high profile project within your organization. You want to identify the project stakeholders that will have the most power in relation to their interest on your project. This will help you plan for project risks, stakeholder management, and ongoing communication with the key stakeholders in your project. In this process of stakeholder analysis, what type of a grid or model should you create based on these conditions?

Options

  • AStakeholder power/interest grid
  • BInfluence/impact grid
  • CSalience model
  • DStakeholder register

How the community answered

(30 responses)
  • A
    87% (26)
  • B
    7% (2)
  • C
    3% (1)
  • D
    3% (1)

Explanation

The power/interest grid maps stakeholders on two axes: level of authority (power) and level of concern about project outcomes (interest). It directly answers the need to identify who has the most power relative to their interest, which guides communication and engagement strategies. The influence/impact grid (B) maps stakeholders by their ability to influence the project against the impact of project decisions on them. The salience model (C) uses three dimensions: power, urgency, and legitimacy. The stakeholder register (D) is a document, not an analytical grid.

Topics

#Stakeholder Analysis#Power-Interest Grid#Stakeholder Identification