nerdexam
PMIPMI

PMI-RMP · Question #36

PMI-RMP Question #36: Real Exam Question with Answer & Explanation

The correct answer is A: Stakeholder power/interest grid. See the full explanation below for the reasoning.

Stakeholder Engagement

Question

You are the project manager for BlueWell Inc. Your current project is a high priority and high profile project within your organization. You want to identify the project stakeholders that will have the most power in relation to their interest on your project. This will help you plan for project risks, stakeholder management, and ongoing communication with the key stakeholders in your project. In this process of stakeholder analysis, what type of a grid or model should you create based on these conditions?

Options

  • AStakeholder power/interest grid
  • BInfluence/impact grid
  • CSalience model
  • DStakeholder register

Topics

#Stakeholder Analysis#Power-Interest Grid#Stakeholder Identification

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions