nerdexam
PMIPMI

PMI-RMP · Question #385

PMI-RMP Question #385: Real Exam Question with Answer & Explanation

The correct answer is B: Discuss the project schedule with the executive sponsor and agree on a strategy for updating the. See the full explanation below for the reasoning.

Stakeholder Engagement

Question

A project manager is hired as a consultant by the executive sponsor to manage a major change program that has experienced two past failures. The current executive sponsor believes the project is in good shape based on feedback from the last project manager and reports this to senior executive management. The executive sponsor believes there were no major risks threatening the time, budget, or quality of the project. In the first week of risk analysis, the project manager concludes the project timeline is unrealistic and is three months behind schedule. The organization's risk appetite is low. What is the first step that should be taken?

Options

  • AReview the project schedule and recommend fast tracking the schedule and/or crashing the
  • BDiscuss the project schedule with the executive sponsor and agree on a strategy for updating the
  • CUpdate existing risk response plans and include more resources to get the project back on track.
  • DImmediately call a steering committee meeting, report the project status, and suggest project

Topics

#Stakeholder Management#Risk Communication#Executive Sponsor Alignment#Schedule Management

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions