nerdexam
PMI

PMI-RMP · Question #385

A project manager is hired as a consultant by the executive sponsor to manage a major change program that has experienced two past failures. The current executive sponsor believes the project is in go

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #385. The question stem and answer options stay visible for context.

Stakeholder Engagement

Question

A project manager is hired as a consultant by the executive sponsor to manage a major change program that has experienced two past failures. The current executive sponsor believes the project is in good shape based on feedback from the last project manager and reports this to senior executive management. The executive sponsor believes there were no major risks threatening the time, budget, or quality of the project. In the first week of risk analysis, the project manager concludes the project timeline is unrealistic and is three months behind schedule. The organization's risk appetite is low. What is the first step that should be taken?

Options

  • AReview the project schedule and recommend fast tracking the schedule and/or crashing the
  • BDiscuss the project schedule with the executive sponsor and agree on a strategy for updating the
  • CUpdate existing risk response plans and include more resources to get the project back on track.
  • DImmediately call a steering committee meeting, report the project status, and suggest project

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Management#Risk Communication#Executive Sponsor Alignment#Schedule Management
Full PMI-RMP Practice