PMIPMI
PMI-RMP · Question #384
PMI-RMP Question #384: Real Exam Question with Answer & Explanation
The correct answer is D: High probability/high impact. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
In the country where a project is being executed, customs procedures are complex and change frequently. During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to the project cancellation. How should the probability and impact be characterized for this risk?
Options
- ALow probability/low impact
- BHigh probability/low impact
- CLow probability/high impact
- DHigh probability/high impact
Topics
#Qualitative Risk Analysis#Probability Assessment#Impact Assessment#Risk Characterization
Community Discussion
No community discussion yet for this question.