PMI-RMP · Question #349
What would be the next step after determining the agreed-upon risk response for a specific risk?
The correct answer is D. Communicate to stakeholders. Once the risk response has been agreed upon by the risk owner and the project team, the immediate next step is to communicate that response to relevant stakeholders. Effective risk management requires that stakeholders be informed of how specific risks will be handled so they…
Question
What would be the next step after determining the agreed-upon risk response for a specific risk?
Options
- AAdd the risk response to the project management plan and document the predicted exposure.
- BEvaluate the project related implications and update the risk response to the project management
- CDocument the predicted exposure
- DCommunicate to stakeholders
How the community answered
(18 responses)- A6% (1)
- B17% (3)
- C6% (1)
- D72% (13)
Explanation
Once the risk response has been agreed upon by the risk owner and the project team, the immediate next step is to communicate that response to relevant stakeholders. Effective risk management requires that stakeholders be informed of how specific risks will be handled so they can align expectations, adjust plans, and provide support or resources as needed. While updating the project management plan and documenting predicted exposure (Options A, B, C) are also necessary steps, communication to stakeholders is the critical follow-on action that enables organizational alignment and accountability. Without timely communication, even a well-designed risk response can fail due to lack of awareness or buy-in from key parties.