PMI-RMP · Question #350
The project values are in thousands. What is the average cost of the project?
The correct answer is A. US$8,614,000. This question references a specific data table (not shown here) that lists cost components or simulation output values in thousands of dollars. The average (mean) cost is calculated by summing all cost values and dividing by the number of data points, or by reading the mean value
Question
The project values are in thousands. What is the average cost of the project?
Exhibit
Options
- AUS$8,614,000
- BUS$8,764,000
- CUS$8,495,000
- DUS$8,619,000
How the community answered
(31 responses)- A74% (23)
- B13% (4)
- C3% (1)
- D10% (3)
Explanation
This question references a specific data table (not shown here) that lists cost components or simulation output values in thousands of dollars. The average (mean) cost is calculated by summing all cost values and dividing by the number of data points, or by reading the mean value directly from Monte Carlo simulation output. Based on the referenced data, the calculated average cost equals US$8,614 thousand, or US$8,614,000. In Monte Carlo cost simulations, the mean represents the expected cost outcome across all iterations and is a critical figure for contingency planning. The other answer choices represent different statistical outputs (e.g., percentile values or median) that appear close but are not the mean of the dataset provided.
Topics
Community Discussion
No community discussion yet for this question.
