nerdexam
PMI

PMI-RMP · Question #386

Which of the following could be included in risk monitoring and controlling techniques?

The correct answer is B. Status review meetings, variance analysis, trend analysis, earned value analysis, inspection,. Options A, C, and D each contain a management/motivation theory that has no place in risk monitoring: 'McGregor's analysis' (Theory X/Y-a leadership model) appears in A, and 'Maslow's analysis' (hierarchy of needs-a motivation model) appears in C and D. Option B contains only val

Risk Monitoring and Reporting

Question

Which of the following could be included in risk monitoring and controlling techniques?

Options

  • AStatus review meetings, trend analysis, earned value analysis, McGregor's analysis, defect repair,
  • BStatus review meetings, variance analysis, trend analysis, earned value analysis, inspection,
  • CStatus review meetings, control charts, Inspection, defect repair, Maslow's analysis, trend
  • DVariance analysis, trend analysis, earned value analysis, Maslow's analysis, control charts,

How the community answered

(24 responses)
  • B
    92% (22)
  • C
    4% (1)
  • D
    4% (1)

Explanation

Options A, C, and D each contain a management/motivation theory that has no place in risk monitoring: 'McGregor's analysis' (Theory X/Y-a leadership model) appears in A, and 'Maslow's analysis' (hierarchy of needs-a motivation model) appears in C and D. Option B contains only valid project monitoring tools: status review meetings, variance analysis, trend analysis, earned value analysis (EVM), inspection, and defect repair-all recognized techniques in the PMBOK for monitoring and controlling project work and risks.

Topics

#Risk monitoring techniques#Risk control techniques#Earned Value Analysis#Variance and Trend Analysis

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice