PMI-RMP · Question #387
Project stakeholders identify, analyze, and plan the risk responses for a project. However, the contingency reserves are depleted before the project is completed. What recommendation could be implemen
The correct answer is C. Conduct more frequent reserve watch list status meetings.. The root problem is that reserves were consumed without adequate ongoing visibility-the team did not detect the drawdown rate in time to take corrective action. Conducting more frequent reserve watch list status meetings directly addresses this by increasing the cadence of monito
Question
Project stakeholders identify, analyze, and plan the risk responses for a project. However, the contingency reserves are depleted before the project is completed. What recommendation could be implemented to prevent this from recurring?
Options
- AUse the Monte Carlo simulation.
- BImplement a reserve analysis process.
- CConduct more frequent reserve watch list status meetings.
- DIncrease the contingency reserve.
How the community answered
(65 responses)- A2% (1)
- B5% (3)
- C83% (54)
- D11% (7)
Explanation
The root problem is that reserves were consumed without adequate ongoing visibility-the team did not detect the drawdown rate in time to take corrective action. Conducting more frequent reserve watch list status meetings directly addresses this by increasing the cadence of monitoring reserve consumption against remaining risk exposure. Option D (increase reserves) treats the symptom rather than the monitoring process. Option A (Monte Carlo) is a quantitative analysis tool used during planning to size reserves, not to monitor them during execution. Option B (reserve analysis process) is a step in the right direction but is less specific than the proactive monitoring cadence that frequent watch list meetings provide.